V2 Implementation Schedule

V2Master

Introduction

  1. Overall target: Ready for public release by 30 May 2013

Implementation Tracks

  1. MAPS Implementation
  2. V2 Implementation
  3. Administration - Administrative work
  4. Marketing - Preparation of web site and marketing material
  5. Infrastructure - System administration

Details in the following sections

MAPS Implementation

  1. (end-Jan) Rough used/admin with database
  2. Payment system working
  3. (end-Feb) CSS with nice layout and User Authorization
  4. Invoices, receipts
  5. Recurring payments
  6. Internationalization

V2 Implementation

  1. Documents, revisions, files
  2. Site/instance configuration
  3. File upload/download
  4. (mid-Feb) User and user role management
  5. CSS and layout
  6. Tasks (simple workflow), notes
  7. Link docs, rev, tasks
  8. Notifications

Administration

  1. SixPayment signup

  2. (start-Feb) Clarification of VAT
  3. Terms & Conditions (AGB)

Marketing

  1. Pricing model
  2. 2-pager product description
  3. Wire frames of web site
  4. Write web pages
  5. CSS

Infrastructure

  1. (done) Setup host system
  2. (done) Setup git host
  3. (end-Feb) Automated deployment
  4. Automated monitoring
  5. Host VM provisioning?